Short Term Goals
Short Term Goals
1. Plaza improvements/fencing of the open areas
2. Planning for the model portion of the building.
3. Canopy Stabilization
4. Roof issues/drains completed.
5. Obtain foundation funding
6. Re-establishing basic infrastructure including electric,
water, and communication services
2005
At the January 2005 Planning session a request was made to estimate the cost associated with a variety of capital improvement projects. This cost estimate would then become the basis to initiate a search for grants and their
eventual procurement. To this end, Jeff Ingersoll and Jim Mruk calculated the following estimates based on data collected from the most recent temporary protection project of 2002/2003.
Baggage and Mail Building:
$100k Window Board-up
175k Roofing
225k Debris removal
$500k total
The second part of this estimate addresses debris removal only in the following areas.
1. 7 story office area — $188,000
2. South of Curtis St Lower levels — 54,000.
3. Tower (6 floors only)– 72,000
$314,000 Total